A project has to be completed in at most 14 days. 25 men can finish it in 12 days working 6 hours a day. 25 men started working 8 hours a day, but after 4 days 15 men left. What is the minimum number of hours per day the remaining men must work to complete the project before the deadline?

  1. 7
  2. 10
  3. 9
  4. 8
Answer (Detailed Solution Below)
Option 2 : 10

Detailed Solution

Concept approach

Work = 25 × 12 × 6 = 1800 man-hours; done 25 × 4 × 8 = 800

⇒ remaining 1000 by 10 men in 10 days

⇒ 10 hours