A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

(SSC CGL Tier-1 2023 (17 Jul · Shift 2 · 11:45 AM))
  1. 38 1/12
  2. 36½
  3. 36
  4. 39 1/12
Answer (Detailed Solution Below)
Option 1 : 38 1/12

Detailed Solution

Concept approach

LCM 600

⇒ eff 20, 15, 12

⇒ 3 days = 47

⇒ 12 cycles = 36 days = 564

⇒ left 36: A 20, B 15 (2 days)

⇒ 1 left, C = 1/12 day

⇒ 38 1/12 days