A completes 75% of a work in 12 days and B completes 125% of the work in 10 days. In how many days can A and B together complete 75% of the work?

  1. 4 days
  2. 6 days
  3. 5 days
  4. 10 days
Answer (Detailed Solution Below)
Option 1 : 4 days

Detailed Solution

Concept approach

A: 75% in 12 days

⇒ B: 125% in 10 days

⇒ 75% in 6 days. A = 12, B = 6 (days for 75%)

⇒ efficiency 1 : 2

⇒ work = 12 units, A+B = 3

⇒ 12/3 = 4 days