Bob can finish a job in 40 days working alone. Alex is twice as fast as Bob and thrice as fast as Cole. Alex and Bob work on the first day, Bob and Cole on the second day, Cole and Alex on the third day, and they repeat this three-day roster. For how many days in total would Alex have worked when the job gets finished?
- 12
- 10
- 9
- 11
Answer (Detailed Solution Below)
Option 4 : 11
Detailed Solution
Concept approach
A : B : C = 6 : 3 : 2, work = 120. AB = 9, BC = 5, CA = 8
⇒ 3 days = 22
⇒ 15 days = 110; day 16 (AB)
⇒ 119; day 17 (BC) finishes. Alex worked 10 + 1 = 11 days
Ultra Calci trickLCM work / efficiency
Bob 40 d, Alex 20 d, Cole 60 d
⇒ LCM 120
⇒ efficiency B 3, A 6, C 2
3-day roster = (6+3) + (3+2) + (2+6) = 22
⇒ 5 rosters = 110 in 15 days (Alex 2 days each = 10)
Left 10: day 16 (A+B) = 9 → 119; day 17 (B+C) = 5 finishes
⇒ Alex = 10 + 1 = 11 ✓
बॉब अकेले काम करता है तो एक काम 40 दिनों में पूरा कर सकता है। एलेक्स, बॉब से दोगुना और कोल से तीन गुना तेज़ है। पहले दिन एलेक्स और बॉब, दूसरे दिन बॉब और कोल, तीसरे दिन कोल और एलेक्स काम करते हैं और यही तीन दिवसीय क्रम दोहराते हैं। काम समाप्त होने पर एलेक्स ने कुल कितने दिन काम किया होगा?
- 12
- 10
- 9
- 11
उत्तर (विस्तृत हल नीचे)
विकल्प 4 : 11
विस्तृत हल
कॉन्सेप्ट से हल
A : B : C = 6 : 3 : 2, कार्य 120
⇒ 15 दिन में 110, 16वें दिन AB, 17वें दिन BC
⇒ एलेक्स 11 दिन
अल्ट्रा कैलसी ट्रिकLCM work / efficiency
Bob 40 दिन, Alex 20 दिन, Cole 60 दिन
⇒ LCM 120
⇒ दक्षता B 3, A 6, C 2
3 दिन का चक्र = (6+3) + (3+2) + (2+6) = 22
⇒ 5 चक्र = 15 दिन में 110 (Alex के 2 × 5 = 10 दिन)
शेष 10: दिन 16 (A+B) = 9 → 119; दिन 17 (B+C) = 5 से पूरा
⇒ Alex = 10 + 1 = 11 ✓