A team of 12 workers can complete a project in 15 days by working 8 hrs a day. After working for 5 days, 4 workers fall sick and leave the project. The management requests the remaining workers to complete the project in the originally scheduled 15 days due to urgency. How many hours a day must the remaining workers work to complete the work within the specified time?

(SSC CGL 2026 (24 Oct, Shift 3))
  1. 12 hrs
  2. 11 hrs
  3. 10 hrs
  4. 9 hrs
Answer (Detailed Solution Below)
Option 1 : 12 hrs

Detailed Solution

Concept approach

Total work = 12×15×8 = 1440 man-hr. 5 days done = 480

⇒ left 960. 8 workers × 10 days × h = 960

⇒ h = 12 hrs/day.