A and B together can complete a piece of work in 25 days, B and C together can complete the same piece of work in 36 days, while C and A together can complete it in 30 days. If A, B, C, and D together can complete this piece of work in 18 days, then in how many days can D alone complete this piece of work?

(SSC CPO Paper-1 2024 (28 Jun 2024, Shift 1))
  1. 210
  2. 180
  3. 200
  4. 225
Answer (Detailed Solution Below)
Option 3 : 200

Detailed Solution

Concept approach

LCM(25, 36, 30, 18) = 900

⇒ A+B = 36, B+C = 25, C+A = 30

2(A+B+C) = 91

⇒ A+B+C = 45.5

A+B+C+D = 900/18 = 50

⇒ D = 4.5

days = 900/4.5 = 200