A and B can do a piece of work in 12 days and 15 days, respectively. Both work for 4 days and then A leaves. How long (in days) will B take to complete the remaining work?

(RRB NTPC Undergraduate CBT-1 2026 (15 Jun 2026, Shift 3))
  1. 8
  2. 6
  3. 7
  4. 5
Answer (Detailed Solution Below)
Option 2 : 6

Detailed Solution

Concept approach

LCM(12, 15) = 60

⇒ A = 5, B = 4

4 days = 36

⇒ left = 24

B alone = 24/4 = 6 days