(B + C) take 50% more time than (A + B + C). If all three take ₹450 for a work, B's share is ₹120. In how many days will (A + B + C) complete the work if (A + B) take 8/3 days more than (A + B + C)?

  1. 3 days
  2. 3.5 days
  3. 4 days
  4. 4.5 days
Answer (Detailed Solution Below)
Option 3 : 4 days

Detailed Solution

Concept approach

B + C : ABC efficiency = 2 : 3

⇒ A = 1/3 of ABC. B = 120/450 = 4/15 of ABC. Take ABC = 15

⇒ A = 5, B = 4

⇒ A + B = 9. Times ABC : AB = 3 : 5

⇒ 2 parts = 8/3

⇒ ABC = 4 days