12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting, 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting?

(SSC MTS 2021 (11 Oct 2021, Shift 1))
  1. 4
  2. 6
  3. 8
  4. 5
Answer (Detailed Solution Below)
Option 2 : 6

Detailed Solution

Concept approach

12 men × 8 = 96 units; 16 women × 12 = 192

⇒ 1 man = 2 women.

8 men × 6 days = 48

⇒ left 48; now 6 men + 4 women = 6 + 2 = 8 men

⇒ 48 ÷ 8 = 6 days

⇒ B.

Ultra Calci trickefficiency units

12M × 8 = 16W × 12 → 96M = 192W → M = 2, W = 1 unit → work = 192

8 men × 6 days = 96 → left 96; then 6 men + 4 women = 12 + 4 = 16 per day

96/16 = 6 days

⇒ 6