इस सवाल को देखें:
12 men can complete a painting work in 8 days. However, 16 women can complete the same painting work in 12 days. 8 men started painting the house. After 6 days of painting, 2 men were replaced by 4 women. Now how many days will they take to complete the remaining painting?
(SSC MTS 2021 (11 Oct 2021, Shift 1))
- 4
- 6
- 8
- 5
Answer (Detailed Solution Below)
Option 2 : 6
Detailed Solution
Concept approach
12 men × 8 = 96 units; 16 women × 12 = 192
⇒ 1 man = 2 women.
8 men × 6 days = 48
⇒ left 48; now 6 men + 4 women = 6 + 2 = 8 men
⇒ 48 ÷ 8 = 6 days
⇒ B.
Ultra Calci trickefficiency units
12M × 8 = 16W × 12 → 96M = 192W → M = 2, W = 1 unit → work = 192
8 men × 6 days = 96 → left 96; then 6 men + 4 women = 12 + 4 = 16 per day
96/16 = 6 days
⇒ 6
12 पुरुष एक पेंटिंग कार्य को 8 दिनों में पूरा कर सकते हैं। जबकि, 16 महिलाएँ उसी पेंटिंग कार्य को 12 दिनों में पूरा कर सकती हैं। 8 पुरुषों ने घर की पेंटिंग शुरू की। 6 दिनों की पेंटिंग के बाद, 2 पुरुषों के स्थान पर 4 महिलाओं को लगा दिया गया। अब शेष पेंटिंग पूरी करने में उन्हें कितने दिन लगेंगे?
(SSC MTS 2021 (11 Oct 2021, Shift 1))
- 4
- 6
- 8
- 5
उत्तर (विस्तृत हल नीचे)
विकल्प 2 : 6
विस्तृत हल
कॉन्सेप्ट से हल
12 पुरुष × 8 = 96 इकाई; 16 महिला × 12 = 192
⇒ 1 पुरुष = 2 महिला।
8 × 6 = 48 हो गया, शेष 48; अब 6 पुरुष + 4 महिला = 6 + 2 = 8 पुरुष
⇒ 48 ÷ 8 = 6 दिन
⇒ B।
अल्ट्रा कैलसी ट्रिकefficiency units
12M × 8 = 16W × 12 → 96M = 192W → M = 2, W = 1 इकाई → काम = 192
8 पुरुष × 6 दिन = 96 → शेष 96; फिर 6 पुरुष + 4 महिलाएँ = 12 + 4 = 16 प्रतिदिन
96/16 = 6 दिन
⇒ 6