A can do a piece of work in 20 days and B in 10 days. With the help of C, the three together finished the work in 5 days. In how many days can C alone finish the work?

(SSC CHSL 2024)
  1. 25
  2. 10
  3. 20
  4. 15
Answer (Detailed Solution Below)
Option 3 : 20

Detailed Solution

Concept approach

In 5 days A = 25%, B = 50%

⇒ C = 25% in 5 days

⇒ 20 days