A, B and C together can complete a work in 12 days. A as well as B alone can do the same work in 36 days. In how many days can C alone complete the same work?

(SSC CGL Tier-1 2023 (24 Jul · Shift 3 · 2:30 PM))
  1. 48
  2. 25
  3. 12
  4. 36
Answer (Detailed Solution Below)
Option 4 : 36

Detailed Solution

Concept approach

LCM 36

⇒ A + B + C = 3, A = 1, B = 1

⇒ C = 1

⇒ 36 days