A can do a piece of work in 8 days, while B can do it in 7 days. If they work at it alternately beginning with A, then in how many days will the work be completed?

(SSC CPO Paper-1 2023 (03 Oct 2023, Shift 2))
  1. 8
  2. 8½
  3. 7½
  4. 7
Answer (Detailed Solution Below)
Option 3 : 7½

Detailed Solution

Concept approach

Work = LCM(8, 7) = 56: A = 7/day, B = 8/day

⇒ 2 days = 15. 3 pairs = 45 in 6 days.

Day 7 A: 52; remaining 4 by B = 4/8 = 1/2 day

⇒ 7 1/2 days.