A can do a piece of work in 15 days. B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:

(SSC CGL Mains 2019 (15.11.2020))
  1. 3 days
  2. 2 1/2 days
  3. 4 days
  4. 3 1/2 days
Answer (Detailed Solution Below)
Option 1 : 3 days

Detailed Solution

Concept approach

A = 4, B = 5, C = 7

⇒ total = 60. A + C for 3 days = 33

⇒ left 27 ÷ (A + B = 9) = 3 days

Ultra Calci trickefficiency units

Work 60: A 4/day; B 25% more = 5; C 40% more than B = 7

A + C for 3 days = 33 → 27 left; A + B = 9/day

27/9

⇒ 3 days ✓