A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?

(SSC CGL Tier-1 2025 (12 Sep · Shift 2 · 12:30 PM))
  1. 25 days
  2. 18 days
  3. 16 days
  4. 12 days
Answer (Detailed Solution Below)
Option 1 : 25 days

Detailed Solution

Concept approach

Total 90: A 3, B 2, C 1 per day

Every 5th day all three: 4 × 3 + 6 = 18 per 5 days

⇒ 90/18 = 5 cycles = 25 days