A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B left off 8 days and C six days before the completion of the work. In what time is the work finished?

(SSC CGL Mains 2015 (25.10.2015))
  1. 10 days
  2. 9 days
  3. 12 days
  4. 14 days
Answer (Detailed Solution Below)
Option 3 : 12 days

Detailed Solution

Concept approach

Total = 96; A 6, B 3, C 2. 6T + 3(T − 8) + 2(T − 6) = 96

⇒ 11T = 132

⇒ T = 12 days

Ultra Calci trickLCM work

LCM 96 → A = 6, B = 3, C = 2 per day; total time T: A works T, B (T − 8), C (T − 6)

6T + 3(T − 8) + 2(T − 6) = 96

⇒ 11T = 132

⇒ T = 12

Check: 72 + 12 + 12 = 96 ✓

⇒ 12 days