Rajan and Rajat can do a work in 64 days and 48 days, respectively. Starting with Rajat, they work on alternate days. In how many days will the work be completed?

(SSC CPO Paper-1 2024 (29 Jun 2024, Shift 2))
  1. 55
  2. 54¾
  3. 54
  4. 55¾
Answer (Detailed Solution Below)
Option 2 : 54¾

Detailed Solution

Concept approach

LCM = 192: Rajan 3/day, Rajat 4/day. Rajat first

⇒ 2 days = 7 units.

27 pairs = 54 days = 189; left 3

⇒ Rajat needs 3/4 day

⇒ 54 3/4 days