Selection KeySelection KeyFree Mock Test
View this question in:

A, B, C and D can complete a work individually in 16 days, 24 days, 48 days and 32 days, respectively. All four work together for 4 days. Thereafter A works at 75% of his original efficiency, B at 150%, C at 250% and D at 80%. How much total time, from the start, is required to complete the work?

(SSC CGL 2026 (23 Oct, Shift 2))
  1. 5 173/179 days
  2. 6 days
  3. 6 1/179 days
  4. 6 2/179 days
Answer (Detailed Solution Below)
Option 4 : 6 2/179 days

Detailed Solution

Concept approach

LCM 96: A 6, B 4, C 2, D 3 = 15/day. 4 days = 60, left 36. New: 4.5 + 6 + 5 + 2.4 = 17.9/day

⇒ 36/17.9 = 360/179 days. Total = 4 + 360/179 = 6 2/179 = 6·2/179 days.

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →