A can complete a piece of work in 4 days, while B can complete the same work in 52 days. B works alone for 13 days and then leaves. In how many days can A alone complete the remaining work?

(RRB JE CBT-1 2026 (27 Oct 2026, Shift 3))
  1. 4
  2. 5
  3. 2
  4. 3
Answer (Detailed Solution Below)
Option 4 : 3

Detailed Solution

Concept approach

B in 13 days does 13/52 = 1/4

⇒ remaining 3/4

A's 1 day = 1/4

⇒ 3/4 ÷ 1/4 = 3 days