A can complete a piece of work in 24 days and B can complete it in 28 days. If they work on alternate days, starting with B on the first day, then in how many days will the work be finished?

(RRB NTPC Graduate CBT-1 2025 (12 Jun 2025, Shift 1))
  1. 25⁶⁄₇
  2. 24⁶⁄₇
  3. 24⅙
  4. 25⅙
Answer (Detailed Solution Below)
Option 1 : 25⁶⁄₇

Detailed Solution

Concept approach

Total = LCM(24, 28) = 168

⇒ A = 7, B = 6 per day

⇒ pair = 13

12 pairs = 24 days = 156

⇒ left 12

Day 25: B does 6, left 6

⇒ A needs 6/7 day

⇒ 25 6/7 days