64 persons can dig a trench 50 m long, 2 m wide and 2 m deep in 5 days working 12 hours daily. In how many days, working 8 hours daily, will 80 persons dig another trench 75 m long, 4 m wide and 3 m deep?

  1. 27
  2. 18
  3. 36
  4. 45
Answer (Detailed Solution Below)
Option 1 : 27

Detailed Solution

Concept approach

64 × 12 × 5/(50 × 2 × 2) = 80 × 8 × x/(75 × 4 × 3)

⇒ x = 27 days

Ultra Calci trickmultiple-of-27

Days = 5 × 12/8 × 64/80 × (75×4×3)/(50×2×2) = 5 × 3/2 × 4/5 × 9/2

Numerators 3 and 9 → no 3 in any denominator → multiple of 27

18 ✗ 36 ✗ 45 ✗ 27 ✓

⇒ 27 days