A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days, and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would the work have been finished?

  1. 5
  2. 6
  3. 7
  4. 8
Answer (Detailed Solution Below)
Option 1 : 5

Detailed Solution

Concept approach

Work = 100 × 35 + 200 × 5 = 4500 man-days

⇒ 100 men need 45 days

⇒ 5 days late