P and Q can do a work together in 30 days. Q and R can do the same work together in 24 days and R and P together in 20 days. They started the work together, but Q and R left after 10 days. How many more days will P take to finish the remaining work?

(SSC CPO Paper-1 2023 (03 Oct 2023, Shift 2))
  1. 23
  2. 21
  3. 18
  4. 19
Answer (Detailed Solution Below)
Option 3 : 18

Detailed Solution

Concept approach

LCM(30, 24, 20) = 120

⇒ P+Q = 4, Q+R = 5, R+P = 6

2(P+Q+R) = 15

⇒ P+Q+R = 7.5

⇒ P = 2.5, Q+R = 5

10 days: 10 × 7.5 = 75

⇒ left 45

45/2.5 = 18 days