A can do 20% of a work in 4 days, B can do 33⅓% of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together will complete 75% of the same work in:

(SSC CGL Mains 2019 (15 Nov 2020))
  1. 15 days
  2. 12 days
  3. 10 days
  4. 9 days
Answer (Detailed Solution Below)
Option 3 : 10 days

Detailed Solution

Concept approach

A: 20% in 4 d

⇒ 20 d; B: 33⅓% in 10 d

⇒ 30 d; LCM 60: A = 3, B = 2

9 days × 5 = 45

⇒ left 15 done by C in 6 d

⇒ C = 2.5/day

B + C = 4.5/day; 75% = 45

⇒ 45/4.5 = 10 days