Selection KeySelection KeyFree Mock Test
View this question in:

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

(SSC CGL Tier-1 2023 (25 Jul · Shift 1 · 9:00 AM))
  1. 20
  2. 16
  3. 25
  4. 18
Answer (Detailed Solution Below)
Option 2 : 16

Detailed Solution

Concept approach

32m + 48w = 30m + 70w

⇒ 2m = 22w

⇒ m = 11w

⇒ work = 32 × 11 + 48 = 400

⇒ 400/25 = 16 days