If 1/4th of the work is completed in 2 days, then the work which is equivalent to 4 times the initial work will be completed in

(SSC MTS 2023 (11 May 2023, Shift 1) memory-based)
  1. 16 days
  2. 24 days Page- 1
  3. 64 days
  4. 32 days
Answer (Detailed Solution Below)
Option 4 : 32 days

Detailed Solution

Concept approach

1/4 work in 2 days

⇒ 1 work = 8 days

4 works = 4 × 8 = 32 days