A contractor employed 30 men to do a work in 38 days. After 25 days he employed 5 more men and the work was finished one day earlier. How many days would he have been behind if he had not employed the additional men?

  1. 1 1/2
  2. 1 1/4
  3. 1 3/4
  4. 1
Answer (Detailed Solution Below)
Option 4 : 1

Detailed Solution

Concept approach

Men 30 : 35 = 6 : 7

⇒ days 7 : 6

⇒ 2 parts = 12

⇒ 30 × x = 35 × 12

⇒ x = 14 days vs 13

⇒ 1 day behind