X can complete a work in 2 days and Y in 4 days.
How long will it take them to finish the work if they work together X

(SSC CPO Paper-1 2025 (12 Dec 2025, Shift 1))
  1. 1/2 days
  2. 4/3 days
  3. 3/4 days
  4. 4/7 days
Answer (Detailed Solution Below)
Option 2 : 4/3 days

Detailed Solution

Concept approach

LCM(2, 4) = 4

⇒ X = 2, Y = 1

⇒ 3/day

4/3 days