A man works twice as fast as a woman and a woman works twice as fast as a child. If 18
men can complete a job in 10 days, how many days would 36 women and 72 children together require to finish the same job?

(SSC Selection Post 2026 (Higher Secondary, 18 Sep, Shift 2))
  1. 6 days
  2. 8 days
  3. 5 days
  4. 7 days
Answer (Detailed Solution Below)
Option 3 : 5 days

Detailed Solution

Concept approach

Man = 4 child, woman = 2 child. 18 men = 72 units × 10 days. 36 women + 72 children = 144 units

⇒ 720/144 = 5 days