P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

(SSC CGL Tier-1 2023 (24 Jul · Shift 2 · 11:45 AM))
  1. 10 days
  2. 8 days
  3. 11 days
  4. 9 days
Answer (Detailed Solution Below)
Option 4 : 9 days

Detailed Solution

Concept approach

LCM 18

⇒ P = 1, P + Q = 3

⇒ Q = 2

⇒ 18/2 = 9 days