A and B can complete a piece of work in 10 and 16 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in :

(SSC CGL Tier-1 2022 (6 Dec · Shift 3 · 2:30 PM))
  1. 12¼ days
  2. 13¼ days
  3. 15¼ days
  4. 14¼ days
Answer (Detailed Solution Below)
Option 1 : 12¼ days

Detailed Solution

Concept approach

LCM 80: A = 8, B = 5 per day; 2 days = 13

⇒ 6 pairs (12 days) = 78

Left 2

⇒ A on day 13 does 2/8 = 1/4 day

⇒ 12¼ days

⇒ option A

Ultra Calci trickLCM work, alternate days

LCM 80 → A 8, B 5 → 2 days = 13 → 6 pairs (12 days) = 78

left 2 → A needs 2/8 day → 12¼ days

⇒ 12¼ days

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →