X and Y can complete a work in 9 days and 36 days respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in:

(SSC CGL 14.07.2023)
  1. 12 1/2 days
  2. 14 1/4 days
  3. 13 1/3 days
  4. 15 1/5 days
Answer (Detailed Solution Below)
Option 2 : 14 1/4 days

Detailed Solution

Concept approach

Total = 36; X 4, Y 1

⇒ 5 per 2 days. 14 days = 35; day 15 X needs 1

⇒ 1/4 day

⇒ 14 1/4 days