A and B can finish a certain job in 28 and 35 days, respectively. They started working together, but A left after a while, and B managed to complete the remaining work in 17 days. How many days did A work before leaving?

(SSC CGL Tier-1 2025 (18 Sep · Shift 2 · 12:30 PM))
  1. 8 days
  2. 5 days
  3. 6⁷⁄₂ days
  4. 7⁵⁄₂ days
Answer (Detailed Solution Below)
Option 1 : 8 days

Detailed Solution

Concept approach

Total = LCM(28, 35) = 140

⇒ A = 5, B = 4 per day

⇒ B alone 17 days = 68

⇒ together = 72

⇒ 72/(5 + 4) = 8 days

Ultra Calci trickLCM work

LCM 140 → A 5, B 4 per day; A works t days, B t + 17

5t + 4(t + 17) = 140 → 9t = 72 → t = 8

⇒ 8 days