A alone can complete a piece of work in 200 days, while B alone can complete the same work in 100 days. In each three-day cycle, on the first day both A and B work, on the second day only A works and on the third day only B works. This cycle continues until the work is completed. How many days do they take to complete the work?

(SSC CPO 2024)
  1. 100 1/2
  2. 100
  3. 100 1/3
  4. 99 2/3
Answer (Detailed Solution Below)
Option 4 : 99 2/3

Detailed Solution

Concept approach

A = 0.5%, B = 1% per day

⇒ cycle of 3 days = 1.5 + 0.5 + 1 = 3%

⇒ 33 cycles = 99 days = 99%

⇒ remaining 1% on day 100 by A+B at 1.5%

⇒ 2/3 day

⇒ 99 2/3 days