A can do a piece of work in 15 days. B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C leaves. A and B together will complete the remaining work in:

(SSC CGL Mains 2019 (15 Nov 2020))
  1. 2½ days
  2. 3½ days
  3. 4 days
  4. 3 days
Answer (Detailed Solution Below)
Option 4 : 3 days

Detailed Solution

Concept approach

A = 15 days; B = 1.25 × A; C = 1.4 × B

⇒ efficiencies A : B : C = 4 : 5 : 7 (take A = 1

⇒ B = 1.25, C = 1.75, work = 15)

A + C for 3 days = 2.75 × 3 = 8.25

⇒ left 6.75

A + B = 2.25

⇒ 6.75/2.25 = 3 days

Ultra Calci trickefficiency units

A : B : C = 4 : 5 : 7 (×1.25, ×1.4) → work = 4 × 15 = 60 units

A + C, 3 days = 33 → left 27; A + B = 9/day

27/9

⇒ 3 days ✓