View this question in:

A group of workers working individually can complete the project in 60 days. On the first day, only one worker starts the work. Each subsequent day, one more worker joins the team. That is 1 worker on day 1, 2 workers on day 2, 3 workers on day 3, and so on. Assuming every worker contributes equally and continuously from the day they join, estimate in how many days will the project be completed?

(SSC CGL 2026 (23 Oct, Shift 3))
  1. 10.5
  2. 10
  3. 9.5
  4. 9
Answer (Detailed Solution Below)
Option 1 : 10.5

Detailed Solution

Concept approach

Total work = 60 worker-days. Workers add up: 1+2+…+n = n(n+1)/2 = 60

⇒ n ≈ 10.45. (10 days = 55, remaining 5/11 day)

⇒ ≈ 10.5 days.