A contractor planned to finish a work in 24
days with 15 workers. After 8 days, 5 more workers joined and all workers worked at the same rate. In how many total days was the work finished?

(SSC Selection Post 2026 (Matric, 17 Sep, Shift 3))
  1. 18 days
  2. 20 days
  3. 21 days
  4. 22 days
Answer (Detailed Solution Below)
Option 2 : 20 days

Detailed Solution

Concept approach

Work = 15 × 24 = 360; 8 days: 120 done

⇒ 240 left ÷ 20 workers = 12 days

⇒ 8 + 12 = 20 days