Eight workers working 10 hours a day complete a work in 18 days. If only 5 workers are working, how many hours a day should they work to complete the work in 24 days?

  1. 10 hours
  2. 9 hours
  3. 12 hours
  4. 8 hours
Answer (Detailed Solution Below)
Option 3 : 12 hours

Detailed Solution

Concept approach

8 × 10 × 18 = 5 × 24 × h

⇒ h = 12 hours