If 7 people working 4 hours a day can complete a task in 14 days. The number of days taken by 12 people working 8 hours a day will be:

(SSC CHSL 2023 (04 Aug 2023, Shift 2))
  1. 5⅛ days
  2. 8 days
  3. 4¹⁄₁₂ days
  4. 7¼ days
Answer (Detailed Solution Below)
Option 3 : 4¹⁄₁₂ days

Detailed Solution

Concept approach

Total work = 7 × 4 × 14 = 392 man-hours

Days = 392/(12 × 8) = 392/96 = 4 1/12 days.