Two coal loading machines, each working 12 hours a day for 8 days, handle 9000 tonnes of coal with an efficiency of 90%, while 3 other machines at an efficiency of 80% are set to handle 12000 tonnes in 6 days. How many hours per day should each of them work?

  1. 16
  2. 12
  3. 18
  4. 14
Answer (Detailed Solution Below)
Option 1 : 16

Detailed Solution

Concept approach

2 × 8 × 12 × 90/9000 = 3 × 6 × x × 80/12000

⇒ x = 16 hours