Selection KeySelection KeyFree Mock Test
View this question in:

A does some work while his rival B destroys it. If A starts at 2 pm and B starts destroying at 3 pm, the work finishes at 10 pm. If A starts at 2 pm and B starts at 4 pm, the work finishes at 6 pm. If B does not destroy at all, how many minutes will A take to complete the work?

  1. 144
  2. 140
  3. 120
  4. 264
Answer (Detailed Solution Below)
Option 1 : 144

Detailed Solution

Concept approach

8A − 7B = 4A − 2B

⇒ 4A = 5B

⇒ A = 5, B = 4

⇒ work = 40 − 28 = 12

⇒ A alone 12/5 h = 144 min

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →