A alone completes a work in 20 days. The ratio of efficiency of A and B is 3 : 2 and the ratio of time of B and C is 3 : 4. A started the work; after 2 days B joined him. After working 2 days together A left. B worked alone for 2 days, then C joined him. B and C worked for 4 days, then B left. Now C increased his efficiency by 33.33% and finished the work. Find the total time taken to complete the work.

  1. 22 days
  2. 23 days
  3. 25 days
  4. 36 days
Answer (Detailed Solution Below)
Option 2 : 23 days

Detailed Solution

Concept approach

A : B : C = 6 : 4 : 3, total = 120. Work done: 12 + 20 + 8 + 28 = 68 in 10 days; remaining 52 at C = 4

⇒ 13 days

⇒ total 23 days