X1, X2 and X3 can do a work in 90, 45 and 67.5 days respectively. All three of them began the work together but X2 left 13.5 days before the completion of the work. In how many days was the work completed?

(SSC GD Constable 2024 (20 Feb 2024, Shift 4))
  1. 25 days
  2. 24 days
  3. 18 days
  4. 27 days
Answer (Detailed Solution Below)
Option 4 : 27 days

Detailed Solution

Concept approach

Total = 270 units

⇒ X1 = 3, X2 = 6, X3 = 4 per day (sum 13)

13T − 6 × 13.5 = 270

⇒ 13T = 351

T = 27 days