A and B can complete a task in 20 days and 25 days, respectively. They started working together, but B left after 5 days. How many more days will A take to finish the remaining work?

(RRB NTPC Undergraduate CBT-1 2026 (09 May 2026, Shift 1))
  1. 12 days
  2. 11 days
  3. 10 days
  4. 9 days
Answer (Detailed Solution Below)
Option 2 : 11 days

Detailed Solution

Concept approach

LCM = 100: A = 5, B = 4

5 days together = 45

⇒ remaining 55

A alone = 55/5 = 11 days