Selection KeySelection KeyFree Mock Test
View this question in:

A textile factory has two machines, M1 and M2, that process fabric rolls. M1 can complete a batch in 18 days, and M2 in 12 days. Both machines are scheduled to work alternate days, starting with M1 on Day 1. Due to quality checks, only 80% of M1's work and 90% of M2's work is accepted. Assuming the cycle continues until the entire batch (LCM of their working days) is accepted, in how many total days will the work be completed?

(SSC CGL 2026 (27 Oct, Shift 3))
  1. 17 days
  2. 18 days
  3. 19 days
  4. 20 days
Answer (Detailed Solution Below)
Option 1 : 17 days

Detailed Solution

Concept approach

LCM 36 = batch. M1 = 2/day ×0.8 = 1.6; M2 = 3/day ×0.9 = 2.7. Two days = 4.3. 8 cycles (16 days) = 34.4; left 1.6

⇒ M1 on day 17 finishes exactly

⇒ 17 days.

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →