A textile factory has two machines, M1 and M2, that process fabric rolls. M1 can complete a batch in 18 days, and M2 in 12 days. Both machines are scheduled to work alternate days, starting with M1 on Day 1. Due to quality checks, only 80% of M1's work and 90% of M2's work is accepted. Assuming the cycle continues until the entire batch (LCM of their working days) is accepted, in how many total days will the work be completed?
(SSC CGL 2026 (27 Oct, Shift 3))
- 17 days
- 18 days
- 19 days
- 20 days
Answer (Detailed Solution Below)
Option 1 : 17 days
Detailed Solution
Concept approach
LCM 36 = batch. M1 = 2/day ×0.8 = 1.6; M2 = 3/day ×0.9 = 2.7. Two days = 4.3. 8 cycles (16 days) = 34.4; left 1.6
⇒ M1 on day 17 finishes exactly
⇒ 17 days.
एक कपड़ा फ़ैक्टरी में दो मशीनें M1 और M2 कपड़े के रोल प्रोसेस करती हैं। M1 एक बैच 18 दिनों में और M2 12 दिनों में पूरा कर सकती है। दोनों मशीनें बारी-बारी से एक-एक दिन काम करती हैं, पहले दिन M1 से शुरू करके। गुणवत्ता जाँच के कारण M1 के काम का केवल 80% और M2 के काम का 90% स्वीकार होता है। यह मानते हुए कि चक्र तब तक चलता है जब तक पूरा बैच (उनके कार्य दिवसों का LCM) स्वीकार न हो जाए, काम कुल कितने दिनों में पूरा होगा?
(SSC CGL 2026 (27 Oct, Shift 3))
- 17 दिन
- 18 दिन
- 19 दिन
- 20 दिन
उत्तर (विस्तृत हल नीचे)
विकल्प 1 : 17 दिन
विस्तृत हल
कॉन्सेप्ट से हल
LCM 36 = कुल कार्य। M1 = 2/दिन ×0.8 = 1.6; M2 = 3/दिन ×0.9 = 2.7। दो दिन = 4.3। 8 चक्र (16 दिन) = 34.4; शेष 1.6
⇒ दिन 17 में M1 ठीक पूरा करता है
⇒ 17 दिन।
ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →