A can complete a work in 18 days, while B can complete the same work in 12 days. If they worked together for 6 days and then A left the work, in how many days will B complete the remaining work?

(SSC CHSL 2020 (19 Oct 2020, Shift 1))
  1. 6 days
  2. 2 days
  3. 3 days
  4. 4 days
Answer (Detailed Solution Below)
Option 2 : 2 days

Detailed Solution

Concept approach

LCM(18, 12) = 36 units

⇒ A = 2, B = 3 units/day

6 days together = 6 × 5 = 30

⇒ 6 units left

B alone = 6/3 = 2 days