(N+18) persons, each working for 7.5 hours a day, can complete 48% of a work in 20 days. (N+12) persons can complete the remaining work in 30 days, if each of them works for 6.5 hours per day. Determine the value of N.

(SSC CGL Tier-1 2023 (19 Jul · Shift 1 · 9:00 AM))
  1. 18
  2. 16
  3. 20
  4. 22
Answer (Detailed Solution Below)
Option 1 : 18

Detailed Solution

Concept approach

Work 48 : 52 = 12 : 13

⇒ (N+18) × 7.5 × 20 : (N+12) × 6.5 × 30 = 12 : 13

⇒ 150(N+18) : 195(N+12) = 12 : 13

⇒ 10(N+18) = 12(N+12)... check: 1950(N+18) = 2340(N+12)

⇒ 5(N+18) = 6(N+12)

⇒ N = 18

⇒ A

Ultra Calci tricktest options

N = 18: 36 × 7.5 × 20 = 5400 for 48% → 112.5 per 1%

30 × 6.5 × 30 = 5850 for 52% → 112.5 per 1% ✓

⇒ 18