Ramesh and Ganesh together can complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
- 13.5
- 11
- 12
- 14.5
Answer (Detailed Solution Below)
Option 1 : 13.5
Detailed Solution
Concept approach
(R + G) × 9 = (0.7R + G) × 10
⇒ 2R = G. R = 1, G = 2
⇒ total = 3 × 16 = 48; after 7 days remaining 27
⇒ Ganesh alone 27/2 = 13.5 days
Ultra Calci trickLCM work
Together 1 unit/day, total 16
⇒ after 7 days 9 left. They took 10 days
⇒ rate 0.9
⇒ loss 0.1 = 30% of Ramesh
⇒ R = 1/3, G = 2/3
Ganesh alone: 9 ÷ 2/3 = 13.5
11 ✗ 12 ✗ 14.5 ✗
⇒ 13.5 days
रमेश और गणेश एक साथ 16 दिनों में एक काम पूरा कर सकते हैं। सात दिन साथ काम करने के बाद रमेश बीमार हो गया और उसकी दक्षता 30% गिर गई। परिणामस्वरूप उन्होंने 16 के बजाय 17 दिनों में काम पूरा किया। यदि रमेश के बीमार होने के बाद गणेश अकेले काम करता, तो वह शेष काम कितने दिनों में पूरा करता?
- 13.5
- 11
- 12
- 14.5
उत्तर (विस्तृत हल नीचे)
विकल्प 1 : 13.5
विस्तृत हल
कॉन्सेप्ट से हल
(R + G)·9 = (0.7R + G)·10
⇒ G = 2R
⇒ कुल 48, शेष 27
⇒ 27/2 = 13.5 दिन
अल्ट्रा कैलसी ट्रिकLCM work
साथ में 1 इकाई/दिन, कुल 16
⇒ 7 दिन बाद 9 शेष। 10 दिन लगे
⇒ दर 0.9
⇒ कमी 0.1 = रमेश का 30%
⇒ R = 1/3, G = 2/3
गणेश अकेला: 9 ÷ 2/3 = 13.5
11 ✗ 12 ✗ 14.5 ✗
⇒ 13.5 दिन