P is two times more efficient than Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)

(SSC CGL Tier-1 2023 (14 Jul · Shift 2 · 11:45 AM))
  1. 26
  2. 25
  3. 27
  4. 28
Answer (Detailed Solution Below)
Option 3 : 27

Detailed Solution

Concept approach

Eff P : Q = 2 : 1

⇒ time 1 : 2, diff 1 unit = 40

⇒ P = 40, Q = 80 days

⇒ together 80/3 = 26.67 ≈ 27 days

⇒ C