A and B can do a piece of work in 12 days, B and C can do it in 15 days, while C and A can do it in 20 days. In how long will they complete it working together? Additionally, in how long can A alone do it?

  1. 10 days, 50 days
  2. 20 days, 40 days
  3. 15 days, 20 days
  4. 10 days, 30 days
Answer (Detailed Solution Below)
Option 4 : 10 days, 30 days

Detailed Solution

Concept approach

Total = 60; A+B = 5, B+C = 4, C+A = 3

⇒ A+B+C = 6

⇒ 10 days; A = 6 − 4 = 2

⇒ 30 days